# Two project examples: steel structures to Algeria and Germany

## Two separate shipments

These are two different project shipments. Each was handled as its own Project Forwarding scope, with one point of responsibility from loading to destination. The figures have not been combined, and the customer is not named.

## Part charter to Algeria

In Finland, 144 tonnes of steel structures were loaded, four modules. The part charter went to Algeria, where discharge was completed successfully 14 days later. Wiima was accountable for this chain from loading to discharge.

## Project shipment from Finland to Germany

127 tonnes of steel structures were successfully chartered from Finland to Germany. The shipment consisted of five individual blocks. The largest was over 20 metres long, 6 metres wide and 5 metres high, and it weighed over 37 tonnes. A two-crane tandem lift was required for safe loading on board.

Wiima was accountable for the shipment as one project. Loading, including the tandem lift, and the charter to Germany were part of the same chain.

Part charter to Algeria: four steel modules, 144 tonnes.